It's been some time since I've done some work on the barn loft, and I had new materials waiting in the wings for 8-10 months, but finally, I recently started adding a new section!

Since the end of the previous section had full 2x10 inch (the size of the joists) cross blocks in place, the plan was to use 2x4 inch boards to cross block new sections next to the full-sized cross blocks:

Barn Loft Next Joist and Cross Block


And here are the next seven joists in place:

Barn Loft Next Floor Joists in Place

Another View of Barn Loft Next Floor Joists in Place


I thought it best to work my way out from the previously-built section without blocking and attaching the far end of the new joists so that I could square the joists with the plywood flooring as I went. Also, I used a bar clamp to pull together and straighten the torqued joists:

Adding Barn Loft Floor Joist Cross Pieces Using a Clamp


And here's the first line of cross blocks:

First New Barn Loft Cross Pieces in Place


I also added an extra 2x4 board behind the first joist to just give a little more support under plywood that would extend past the joist next to the barn wall:

Extra Barn Loft Back Joist Suporrt


And here is the section completed with the materials I had, including the second line of 2x4 cross blocks and the far 2x10 cross blocks in place. I decided not to attach that far end to the beam yet to continue to try to make sure the floor stays square as I Lord willing add more plywood over time. This is where our new guest Trina spends the nights :) :

Next Barn Loft 8 Foot Section in Place with Plywood Flooring


As always, we are thankful to God for granting provisions to continue on the homestead!